Case study · fictional district

One flush, from field to data

Cedar Valley Improvement District, Ridge Road.

The segment

Three sections,
two sizes

Cedar Valley is fictional. The numbers are real calculations.

  • S1 · 150 mm × 120 m2,120 L
  • S2 · 200 mm × 200 m6,280 L — the largest main, so it sets the flow
  • S3 · 150 mm × 80 m1,413 L
  • Total · 400 m9,813 L of water to move

The flush

Plan, run, check

  1. 1
    Plan Reaching the 1.5 m/s biofilm scouring target in the 200 mm main takes 2,826 L/min, about 20 psi on a Pollard diffuser. Three water exchanges take about 10.4 minutes.
  2. 2
    Run The crew opens the diffuser to 30 psi, giving 3,479 L/min. Velocity is 1.85 m/s in the 200 mm main and 3.28 m/s in the 150 mm sections. Residual pressure holds at 55 psi.
  3. 3
    Check Turbidity falls from 3.4 to under 1.0 NTU. Chlorine meets target. Every limit passes, and the record is complete before the truck leaves.

The result

A row of data,
not a sheet in a binder

  • Every flush saved with the same fields
  • Export to CSV for trends by segment and season
  • Failed checks visible at a glance
  • Water use per flush, per zone, per year